Definition Of Complete
- Mobile BEACON powers up on battery.
- Power system supports hot-swap or zero-downtime battery change.
- KGX61 and BYO SIM provide site connectivity.
- Camera, intercom, sensor, siren/strobe are mounted and working.
- Dashboard shows location/status, health, signal, battery, and alerts.
- Unit is safe and clean enough for demo or pilot use.
Blockers To Attack First
- Confirm Verkada trial or discounted hardware path.
- Confirm Newcastle PowerSwap lead time and dimensions.
- Lock off-the-shelf NEMA cabinet availability.
- Confirm SIM/data plan and KGX61 BYO SIM behavior.
- Get Blake the dimensions needed for base and mast layout.
Owner To Do Lists
Priority orderedTommy Decisions / Vendors / Product
-
Approve v1 scopeNov. 16
Confirm the first unit is a working demo/pilot unit, not final production. Lock the v1 feature set so we stop redesigning mid-build.
Due: Monday, Nov. 16 -
Push Verkada hardware pathVendor
Get pricing/trial confirmation for KGX61, KCF61, TS12, SV21, BZ32, licenses, mounts, and antenna.
Due: Nov. 16-18 -
Confirm Newcastle PowerSwapPower
Verify battery system cost, stock, dimensions, charger needs, runtime assumptions, and whether we can get it in time.
Due: Nov. 17 -
Order the cabinetCabinet
Buy or source a 36 x 24 x 12 NEMA 4/12 enclosure. First choice: Saginaw. Alternates: Hoffman, Hammond, Wiegmann.
Due: Nov. 18-20 -
Define demo storySales
Decide who we are building the demo for, what problem we show, and what the buyer needs to see in five minutes.
Due: Nov. 20 -
Lock pricing assumptionsBusiness
Create v1 rough sell price, rental price, monthly monitoring/service assumption, and customer-facing package names.
Due: Dec. 11 -
Approve final punch listFinish
Review test results and decide what must be fixed before demo versus what moves to v2.
Due: Dec. 28-30
Blake Build / Layout / Field Practicality
-
Cabinet/base layoutNov. 16
Sketch the cabinet on caster base with mast location, door swing, service access, handles, and center of gravity.
Due: Nov. 16-18 -
Mounting planHardware
Choose mounting locations for camera, intercom, sensor, siren/strobe, antenna, battery tray, PoE gear, fuses, and cable glands.
Due: Nov. 18-20 -
SendCutSend parts listFabrication
List custom parts needed: internal backplate, battery retaining tray, mast brackets, device brackets, rain shields, faceplate, and base adapters.
Due: Nov. 20-25 -
Bench assemblyIntegration
Build the electronics on a temporary board before cabinet install. Validate power, PoE, SIM, device adoption, and cable lengths.
Due: Nov. 30-Dec. 4 -
Physical prototype buildAssembly
Install cabinet, mast, power system, devices, cable glands, internal plate, labeling, strain relief, and weather protection.
Due: Dec. 7-11 -
Field test and burn-inTesting
Run 24-48 hour test for cellular stability, battery runtime, hot-swap, camera view, intercom audio, siren/strobe, and dashboard status.
Due: Dec. 21-24 -
Transport and install notesOps
Document how to roll, lift, charge, deploy, aim, power down, and service the unit without guessing.
Due: Dec. 28-31
Shared Weekly Milestones
Lock the build
Freeze v1 scope, assign owners, order long-lead hardware, select cabinet, confirm power and Verkada path.
Design and procurement push
Finalize cabinet layout, power diagram, cable plan, SendCutSend parts, base/mast concept, and replacement options for anything delayed.
Bench prototype
KGX61 online, SIM tested, Verkada devices adopted, PoE/power validated, dashboard status path started.
Physical prototype assembly
Cabinet/base/mast assembled, devices mounted, power installed, wiring dressed, first full-unit power-up complete.
Software and workflow hardening
Dashboard usable, alert/status logic defined, operator workflow written, demo script drafted, BOM/pricing refreshed.
Field test and burn-in
Run stability testing, battery swap testing, connectivity testing, device testing, and rank the remaining issues.
Demo-ready finish
Fix must-haves, clean the unit, finalize docs, capture photos/video, and prepare the pilot/demo handoff.
My Support Tasks
- Maintain BOM and open decision log.
- Keep this dashboard updated as decisions change.
- Create wiring/power checklist and install/test checklist.
- Build product/demo documentation and dashboard requirements.
- Track risks and call out blockers before they cost us a week.
Next 48 Hours
- Tommy confirms cabinet order path and Verkada/Newcastle availability.
- Blake sketches the physical layout and notes any cabinet size concerns.
- We lock the first SendCutSend part list.
- We confirm what can be bench-tested before all fabrication is done.